Acceptance inspection Before installation begins, an acceptance Inspection and an examination of the premises must be conducted. This is to ensure adherence to the project specifications.
1. Ensure that the condition of the machines and/or equipment delivered is satisfactory and has not been damaged during delivery. Note Any damage upon delivery must immediately be settled with the forwarding agent before the machine is incorporated into the installation.
2. Ensure that the obligations of each party at the point of delivery correspond to what has been agreed into the contract.
3. Check that ventilation has been properly installed and that the intake and evacuation air follows the requirements of the installation instructions for each separate machine.
Installation • Check the performance of the installation against the project specifications. • Conduct a functional inspection where each respective machine is tested in accordance with the accompanying installation instructions.
|